The Project
The Challenge
The client had specified a modular structure to be used as a temporary library. When looking at the foundations, a traditional foundation was cost prohibitive due to the depth of the trenches. As the structure was on the grounds of a school, disruption had to be kept to a minimum.
The Solution
12 RootBase S-Range bases were installed in 2 days, giving 45m2 of foundations down to a depth of 2m. The foundations are fully reusable & can be removed easily once the building reaches the end of its use.
Project Details | |
Product | RootBase S-Range |
Project | 42-3-200 |
Project size | 7.5m x 6.0 |
Completed | May 2018 |
Time on site | 2 day |
Depth of piles | 2m |
Number of bases | 12 |
Our reference | SS-18-4639 |